MINISTRY OF ELECTRIC POWER

Breaking News :

Mon State


Under Construction Projects of Line & Substation in Mon State

No.

Name of Projects

Substation

MVA

Location

1

66kV Thanphyuzayat – Ye Transmission Line (52.6) miles and Substation

Ye Substation

66/11kV , 20 MVA

Mon State (Ye Township , Thanphyuzayat Township)

2

230kV   Mawlamying - Yae Transmission Line (2.1)miles

 

 

Mon State, Mawlamying Township.

Tanintharyi Division , Yae Township.

 

 

 

 

 

 

 

66kV Thanphyuzayat - Ye Transmission Line (52.6) miles and Substation

1. Location                                                     -  Mon State (Ye Township, Thanphyuzayat Township)

2. Scope of Work                                                    

    (A)  Line                                                      -  (52.6) miles

    (B) Substation                                             -                               

          66kV Incoming Bay                               -  (1) Bay

          66kV Transformer Bay                          -  (2) Bays

          66kV Measuring Bay                             - (0.5) Bay

3. Situation of Signing Contract

    Contract No. & Date (Materials)                 -  54/DPTSC (PTP)/2019-2020 (3.6.2020)

    Contractor                                                   -  Khin Maung Nyut Co., Ltd (For Line & Substation)

    Contract No. & Date (line)                          -  30/ DPTSC (PTP)/2020-2021 (5.5.2021)

    Contractor                                                   -  Integral Power Transmission Group Co., Ltd

     Contract No. & Date (Substation)              -  84/ DPTSC (PTP)/2020-2021(29.9.2021)

     Contractor                                                  -  Real Trust Co., Ltd

4. Starting Date of Project (Effective date) -  Line                            -   (5.5.2021)

                                                                           Substation                  -   (29.9.2021)

5. Ending Date of Project (Approximation) - Line                            -   (4.5.2023)

                                                                           Substation                  -   (28.9.2023)   

6. Complete Situation                                   -  Substation

                                                                           Control Building            (36%)

                                                                           Switchyard Foundation (64%)

                                                                           Electrical Installation     (97%)           

                                                                           Line    -  (82.78%)  

66kV Ye Substation

66kV Ye Transmission Line

 

230kV   Mawlamying - Yae Transmission Line (2.1)miles

1.  Location                                                   -   Mon State, Mawlamying Township.

                                                                       -   Tanintharyi Division , Yae Township.

2.  Scope of Work           

          (A)  Line                                                -   (2.1)miles

3.  Situation of Signing Contract

          (A) Line

               Construction                                     -   Project Manager(3) + (Civil) Southen

              Contract No.& Date(Materials)          -   We work 230kV Mawlamying-Myawady

                                                                             (Diversion) Line with the remaining equipments.

4.  Starting Date of Project                            -    (9.1.2022)          

5.  Ending Date of Project (Approximation) -    Line            -  December, 2022

6.  Complete Situation                                   -    Line            -  (100%)(Erection)

230kV Mawlamying – Yae (Diversion) Line