Under Construction Projects of Line & Substation in Mon State
No. |
Name of Projects |
Substation |
MVA |
Location |
1 |
66kV Thanphyuzayat – Ye Transmission Line (52.6) miles and Substation |
Ye Substation |
66/11kV , 20 MVA |
Mon State (Ye Township , Thanphyuzayat Township) |
2 |
230kV Mawlamying - Yae Transmission Line (2.1)miles |
|
|
Mon State, Mawlamying Township. Tanintharyi Division , Yae Township. |
66kV Thanphyuzayat - Ye Transmission Line (52.6) miles and Substation
1. Location - Mon State (Ye Township, Thanphyuzayat Township)
2. Scope of Work
(A) Line - (52.6) miles
(B) Substation -
66kV Incoming Bay - (1) Bay
66kV Transformer Bay - (2) Bays
66kV Measuring Bay - (0.5) Bay
3. Situation of Signing Contract
Contract No. & Date (Materials) - 54/DPTSC (PTP)/2019-2020 (3.6.2020)
Contractor - Khin Maung Nyut Co., Ltd (For Line & Substation)
Contract No. & Date (line) - 30/ DPTSC (PTP)/2020-2021 (5.5.2021)
Contractor - Integral Power Transmission Group Co., Ltd
Contract No. & Date (Substation) - 84/ DPTSC (PTP)/2020-2021(29.9.2021)
Contractor - Real Trust Co., Ltd
4. Starting Date of Project (Effective date) - Line - (5.5.2021)
Substation - (29.9.2021)
5. Ending Date of Project (Approximation) - Line - (4.5.2023)
Substation - (28.9.2023)
6. Complete Situation - Substation
Control Building (36%)
Switchyard Foundation (64%)
Electrical Installation (97%)
Line - (82.78%)
66kV Ye Substation
66kV Ye Transmission Line
230kV Mawlamying - Yae Transmission Line (2.1)miles
1. Location - Mon State, Mawlamying Township.
- Tanintharyi Division , Yae Township.
2. Scope of Work
(A) Line - (2.1)miles
3. Situation of Signing Contract
(A) Line
Construction - Project Manager(3) + (Civil) Southen
Contract No.& Date(Materials) - We work 230kV Mawlamying-Myawady
(Diversion) Line with the remaining equipments.
4. Starting Date of Project - (9.1.2022)
5. Ending Date of Project (Approximation) - Line - December, 2022
6. Complete Situation - Line - (100%)(Erection)
230kV Mawlamying – Yae (Diversion) Line